Estate inspection Churchward House Q4 - 2024 to 2025

Inspection date
19 March 2025

Next inspection date: Check the inspection schedule

Attendees

David Magee

DLO

Daniel Roberts

Pinnacle (Caretaking)

Mark Hill

Contract monitoring team

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Responsible officer
David Magee
Contact details
Repair requests
Action requested Location of issue Reference Target date
Paint over graffiti on stair well ceiling 4th floor down to ground floor 1599181/1 Y 16- 30 April 2025

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested