Laurel Bank Gardens Q2 - 2024 to 2025
Inspection date
13 August 2024
Next inspection date: Check the inspection schedule
Attendees
Housing management (for example ASB, tenancy condition and concerns)
No actions requested
Repairs
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Remove concrete slab in middle of car park | Car park | 1512392/1 | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested