Estate inspection Lancaster Court (1 to 166) Q2 - 2024 to 2025

Inspection date
25 July 2024
Next inspection date
24 October 2024

Attendees

Stephen Mbaluka

Pinnacle (Caretaking)

Leanne Gittens

Contract monitoring team

Tom Hall

DLO

Sarah Wallis

Housing Management

Miranda O’Connell

Resident

Sandra Lawrence

Resident

Housing management (for example ASB, tenancy condition and concerns)

Housing management actions
Action requested Location of issue Reference Target date
Remove items in communal areas Various Not given 02 August 2024

Repairs

Repair requests
Action requested Location of issue Reference Target date
Replace GW Glass 131-166 Fire door 7th floor 1506641/1 29 September 2024
Refit rodding point to bin chute 131-166 Next to 138 1506648/1 29 September 2024
Clear roof outlet 131-166 Entrance canopy lift A 1506653/1 29 September 2024
Weld padlock to gate chain 131-166 ramp to basement area 1506659/1 29 September 2024
Ack fill hole in grass 131-166 in front of 150 1506661/1 29 September 2024
Replace metal bins in playground Childrens playground SRQ1433203 Not given

Planned or cyclical works

Planned or cyclical works
Action requested Location of issue Reference Target date
Clear communal drains All blocks Not given Not given

Grounds maintenance

Resident score for grounds maintenance
2 - Unsatisfactory
Grounds maintenance actions
Action requested Location of issue Reference Target date
Cut down communal shrubs All communal green areas Not given Not given

Pinnacle caretaking

Resident score for pinnacle caretaking
4 - Very good
Pinnacle caretaking actions
Action requested Location of issue Reference Target date
Sweep and wash stairs Blocks 91-105 and 131-166 Not given Not given
Sweep football pitch Opposite block 66-90 Not given Not given
Litter pick Rear of block 106-130 Not given Not given

Other areas (for example street lighting, highways or planning)

No actions requested

Translate this website