Estate inspection Sulivan Court (Blocks M to V) Q1 - 2024 to 2025

Inspection date
28 May 2024
Next inspection date
27 August 2024

Attendees

Adil Benothman

Housing Management

Daniel Bitmead

Electrical Supervisor

Stephen Mbaluka

Pinnacle (Caretaking)

Leanne Gittens

Contract monitoring team

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Repair requests
Action requested Location of issue Reference Target date
Disconnect faulty lift screen from spur ground floor Block 248-262 860503 x1 Not given
Refix metal box lid inside main door to block Block 153-172 860503 x1 Not given

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested