Sulivan Court (Blocks M to V) Q1 - 2024 to 2025
Inspection date
28 May 2024
Attendees
Housing management (for example ASB, tenancy condition and concerns)
No actions requested
Repairs
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Disconnect faulty lift screen from spur ground floor | Block 248-262 | 860503 x1 | Not given |
Refix metal box lid inside main door to block | Block 153-172 | 860503 x1 | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested