Gibbs Green Q4 - 2023 to 2024
Inspection date
20 February 2024
Next inspection date: Check the inspection schedule
Attendees
Housing management (for example ASB, tenancy condition and concerns)
No actions requested
Repairs
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Clear blocked gully | Gibbs Green Estate, o/s flat 119. | 039003x1 | Not given |
Clear blocked gully | Gibbs Green Estate, o/s flat 126. | 039003x1 | Not given |
Refix light fitting to ceiling | Gibbs Green Estate, on 3rd floor of communal stairs, near flat 127. | 858107x1 | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested