Sulivan Court (Blocks M to V) Q3 - 2023 to 2024
Inspection date
7 December 2023
Attendees
Housing management (for example ASB, tenancy condition and concerns)
No actions requested
Repairs
Responsible officer
Tom Hall
Contact details
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Paint bin shed doors black | Block P | 1408788/1 | Not given |
Check ground floor magnets, some not opening straight away, some not locking. | Block R | Not given | Not given |
Secure electric cable ground floor | Block S | 1407427/1 | Not given |
Replace and level 25 broken pathing slabs at entrance outside block | Block S | 1407427/1 | Not given |
Repair hasp and provide FB padlock communal fuse box | Block V | 391727x1 | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested