Estate inspection Sulivan Court (Blocks A to L) Q3 - 2023 to 2024

Inspection date
23 November 2023
Next inspection date
27 February 2024

Attendees

Ian Stewart

Housing Officer (Sands End)

Stephen Mbaluka

Pinnacle (Caretaking)

Andrew West

DLO

Leanne Gittens

Contract monitoring team

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Responsible officer
Tom Hall
Contact details
Repair requests
Action requested Location of issue Reference Target date
Clear gully near 475 Block A (444-484) 039003 x 1 24 January 2024
Replace missing gully near 459 Block A (444-484) 035009 x 1 24 January 2024
Replace glass to balcony 466 Block A (444-484) 520007 x 1 24 January 2024
Window handles to stairs Block A (444-484) 318107 x 2 24 February 2024
Replace cracked glass to front entrance door Block F (65-44) 515005 x 1 24 January 2024
Replace glass to MED Block G (85-104) 515005 x 1 Not given
Leak above lift lobby top floor PPM Block G (85-104) 515005 x 1 Not given
Replace fire exit sign 3 floor Block G (85-104) 029301 x 1 Not given
Repair concrete near lift entrance 391 – urgent trip hazard Block L (372-395) 697001 x 1 24 January 2024
Leak from 394 or 393 affecting communal lights near 391 Block L (372-395) 029301 x 4 24 January 2024
Left hand stairwell - Replace fire exits signs to stairwell 7th, 5th, 4th, and 3rd floor Block L (372-395) 029301 x 4 24 February 2024
Middle stairwell- replace fire exit sign on 4th, 3rd, 2nd, 1st, and ground floor Block L (372-395) Not given 24 January 2024

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested