Estate inspection Creighton Close, Abercrombie and Bathurst houses Q3 - 2023 to 2024

Inspection date
9 November 2023
Next inspection date
22 February 2024

Attendees

Mahamed Mahamoud

Estate compliance team

Kandace Powell

Contract monitoring team

Jeetash Bhandari

DLO

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Repair requests
Action requested Location of issue Reference Target date
Overhaul hopper Abercombie, Block A 3rd Floor Not given Not given
Clear block outlet Abercombie, Block C flat roof above M.E.D Not given Not given
Renew fire exit sign Creighton Close, Block 33 to 48 first floor Not given Not given
Lights off during the day Creighton Close, outside flats 4 and 14 Not given Not given
Overhaul lock Bathurst House, Block A intake cupboard Not given Not given

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

Pinnacle caretaking actions
Action requested Location of issue Reference Target date
Deep clean required All aread to be cleaned Not given 09 December 2023