Estate inspection Churchward House Q2 - 2023 to 2024

Inspection date
21 September 2023
Next inspection date
21 December 2023

Attendees

Simon Pearce

Housing Management

Mark Hill

Contract monitoring team

Paul Brady

DLO Supervisor

Aiden Kenny

DLO

Daniel Roberts

Pinnacle (Caretaking)

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Responsible officer
Tom Hall
Contact details
Repair requests
Action requested Location of issue Reference Target date
Trace leak going into bin shed from flat above [16] Churchward House. Bin shed by main entrance 1368826/1 Not given
Overhaul fire exit door [not shutting properly] Churchward House. Ground Floor. Rear of building 1368829/1 Not given
Renew steel locking post to fire brigade gate. [ Allocate to Brownswood contractor] Fairburn House/ Churchward House, main fire brigade gate. Front of building 1368866/1 Not given
Renew FB padlock and welded chain to gate. [ Allocate to Brownswood contractor]. Churchward House. Rear garden gate 1368838/1 Not given

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested