Wood Lane Estate Q1 - 2023 to 2024
Inspection date
13 June 2023
Attendees
Housing management (for example ASB, tenancy condition and concerns)
Responsible officer
Summer Leach
Contact details
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Items in communal areas | White City Close | Not given | 20 June 2023 |
Grounds maintenance work needed | Grass area | Not given | Not given |
Repairs
Responsible officer
Jeetash Bhandari
Contact details
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Lift and rebed manhole cover and frame | Outside 21 White City Close | Not given | 13 July 2023 |
Renew the sunken tarmac | Outside 9 White City Close | Not given | 13 July 2023 |
Lift and rebed brick paving | Outside 3 White City Close | Not given | 13 July 2023 |
Renew 1 bollard to parking bay and 2 bollards to left of the same parking bay | Outside 33 Exhibition Close | Not given | 13 July 2023 |
Renew 1 missing brick paving | Outside 31 Exhibition Close | Not given | 13 July 2023 |
Rebuild brick pier | Rear of White City Road | Not given | 13 July 2023 |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
Responsible officer
Simon Upperton
Contact details
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Fly-tipping | Exhibition Close | Not given | 13 July 2023 |
Other areas (for example street lighting, highways or planning)
No actions requested