St Peters Terrace Q1 - 2023 to 2024
Inspection date
30 May 2023
Attendees
Housing management (for example ASB, tenancy condition and concerns)
No actions requested
Repairs
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Clear blocked gulley location is the entrance at the top of the ramp, it’s the gulley on the left as you come through the main entrance door. | St Peters Terrace | Not given | 30 July 2023 |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested