Estate inspection Philpott Square Q1 - 2023 to 2024

Inspection date
20 June 2023
Next inspection date
14 September 2023

Attendees

Summer Leach

Estate compliance team

Kandace Powell

Contract monitoring team

Jeetash Bhandari

DLO

Alan Ashelford

Pinnacle (Caretaking)

Housing management (for example ASB, tenancy condition and concerns)

No actions requested

Repairs

Repair requests
Action requested Location of issue Reference Target date
042003 x 43 Hack up and renew Aco drains to the Peterborough Rd side. Philpott Square 1325470/1 20 August 2023
Light out Woodford Court 11th floor near 63 1325470/1 08 July 2023
Renew Georgian wired glass Woodford Court 2nd floor stairwell 1326208/1 08 July 2023
Rub down flaking paint and make good Roseford Court All floors lift walls 1326211/1 08 July 2023
Renew stopcock cupboard door Roseford Court 15th floor outside flat 89 1326228/1 07 July 2023
Rub down flaking paint and make good Roseford Court 4th floor intake cupboard wall 1326234/1 08 July 2023

Planned or cyclical works

No actions requested

Grounds maintenance

No actions requested

Pinnacle caretaking

No actions requested

Other areas (for example street lighting, highways or planning)

No actions requested