Da Palma Court Q1 - 2023 to 2024
Inspection date
9 May 2023
Next inspection date: Check the inspection schedule
Attendees
Housing management (for example ASB, tenancy condition and concerns)
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
No Fly tipping sign needed | Back entrance | Not given | Not given |
Letter to be sent to tenants regarding bikes left outside | Not given | Not given |
Repairs
Action requested | Location of issue | Reference | Target date |
---|---|---|---|
Leaking gutter | Above 19 | Not given | 10 July 2023 |
Make safe spalling concrete to balcony above 10 and 15. Core Projects | Not given | Not given |
Planned or cyclical works
No actions requested
Grounds maintenance
No actions requested
Pinnacle caretaking
No actions requested
Other areas (for example street lighting, highways or planning)
No actions requested