Suspensions and road closures

Need access to a parking bay or bays? What to do and how much notice to give us.

Apply for a parking bay suspension

You can apply for a parking suspension online.

If you're a utility company, you need to apply using the utility company parking suspension form.

Notice periods

Our notice periods depend on the number bays and number of days required for the suspension.

  • Up to six bays for up to three days (8 days notice)
  • Up to six bays for more than three days (2 weeks notice)
  • More than 12 bays for more than a week (4 weeks notice)

Christmas and New Year suspension periods for 2024/25

Our parking centre is closed from 3pm on 24 December 2024 until 2 January 2025. In order to process requests for parking bay suspensions that are required between 24 December 2024 and 18 January 2025, we need to receive your applications by mid December. Please see below for more details.

For suspensions that require 8 days notice
Applications requiring 8 days notice for suspension dates starting: Application form and payment must be received by: Signs must be up by:
24, 25, 26, 24, 27, 28 Dec 2024 16 Dec 17 Dec
29, 30, 31 Dec 2024 17 Dec 18 Dec
2, 3, 4, 5 Jan 2025 18 Dec 19 Dec
6, 7, 8, 9 Jan 2025 19 Dec 20 Dec
10, 11, 12, 13 Jan 2025 20 Dec 21 Dec
For suspensions that require 14 days notice
Applications requiring 14 days notice for suspension dates starting: Application form and payment must be received by: Signs must be up by:
30, 31 Dec 2024 and 1, 2, 3 Jan 2025 16 Dec 17 Dec
4, 5, 6 Jan 2025 17 Dec 18 Dec
7, 8, 9, 10 Jan 2025 18 Dec 19 Dec
11, 12, 13, 14 Jan 2025 19 Dec 20 Dec
15, 16, 17, 18 Jan 2025 20 Dec 21 Dec

We must receive your application and payment by midday on the start date of the notice period you need to give for the suspension

We count Saturdays and Sundays as notification days, you should take these days into account when arranging a suspension.

Depending on the nature of your suspension and the number of days and parking bays required, you may need to notify in writing, anyone who could be affected by the suspension and show evidence that you have done this.

If you need a large suspension for more than a week, call us on 020 7371 5678 Monday to Friday, 9am to 5pm. We need reasonable notice to warn other road users and to place signs around the bays.

When we need eight days notice

If you want to suspend up to six bays (30 metres) for up to three days, we need at least eight days' notice before the suspension date.

For example, if you want the suspension to start on 17 April, we would need your request and payment by midday on 9 April.

However, if the start of your notice period falls on a Saturday or Sunday, we'll need your request and payment by midday on the Friday before.

When we need two weeks notice

We need at least two weeks notice, before the date of suspension, if you want to suspend:

  • up to six bays (30 metres) for more than three days
  • between six and 12 bays for up to a week.

For example, if you want the suspension to start on 15 April, we would need to receive your request and payment by midday on 1 April.

However, if the start of your notice period falls on a Saturday or Sunday, we'll need your request and payment by midday on the Friday before.

When we need four weeks notice

We need at least four weeks notice, before the date of suspension, if you want to suspend:

  • more than 12 bays (60 metres)
  • bays for more than a week.

Charges

The charges for parking bay suspensions increased on 6 November 2024.

The suspension fee is chargeable per day and per five-metre parking bay space. A chargeable day is any day the parking controls would normally apply in the suspended area.

For example, if you need to suspend bays from Thursday to Saturday and the controlled parking hours don't apply on Saturday, then Thursday and Friday are the only chargeable days.

Check the controlled hours for the parking zone you want the suspension in.

The fees per space are:

  • £48 for each of the first 5 chargeable days
  • £74 per day, from day 6 to day 31
  • £99 daily from day 32 to day 93
  • £110 daily from day 94 onward.

Example charges

Example 1: A four-day parking suspension for two bays and each day is chargeable

The cost for this suspension is £384.

To calculate the cost, it is 4 days × £48 × 2 bays.

Example 2: An eight-day parking suspension for three bays and each day is chargeable

The cost for this suspension is £1,386.

To calculcate the cost, the first five days are charged at £48 and the other three days at £74.

So, it is 5 days × £48 × 3 bays. This is £720.

For the other 3 days, it is 3 days × £74 × 3 bays. This is £666.

How to pay

Once you have received your invoice from us, please ensure we receive your payment for your suspension before your deadline date and time.

Payment can be made by credit or debit card over the phone on 020 7371 5678.

We accept the following payment methods:

  • Delta
  • Maestro
  • MasterCard
  • Solo
  • Visa

Please use your suspension number as your reference when you are making the payment.

Or you can pay by bank transfer.

When you have completed the transfer please email parkingsuspensions@lbhf.gov.uk and include:

  • a copy of your remittance advice
  • your suspension reference number
  • your name
  • location of the suspension.

It is the responsibility of the applicant to ensure that full payment is received by the deadline date, or the application will be declined.

Skips and building materials

If you want to place a skip or building materials in a suspended bay, you will also need to apply for and display a skip or materials permit. We only accept applications from skip companies and building contractors for both the suspension and permit.

Apply for a skip permit

Apply for a building materials permit

Utility companies

Contractors working on behalf of a utility company should contact their traffic management officer to ask for a suspension.

Different charging structures apply to utility applications. These are explained on the form.

Film crews

Please ensure you've read the parking bay suspensions for film crews page before you apply.

Film crews applying for a suspension will need to send us and the H&F film office a list of trucks and a diagram showing how they will be parked.

Send your email to parkingsuspensions@lbhf.gov.uk and filmoffice@lbhf.gov.uk and include the reference number for your form.

Amendments and cancellations

We charge a fee of £40 for each amendment or cancellation to an existing parking suspension. We can't process these until you pay this fee.

If you need to change the suspension, you must contact us in writing at least eight days before the new date required.

You must give us at least two working days' notice for all cancellations, otherwise we can't issue a refund.

By submitting your application, you are confirming that you have agreed to the conditions shown on the application form.

Road closures

To find out about road closures in the borough please contact us at traffic.orders@lbhf.gov.uk

To legally close a road in Hammersmith & Fulham you will need a Traffic Management Order and approval from our network management team.

Please visit the traffic management orders page for more information or email traffic.orders@lbhf.gov.uk or londonpermitscheme@lbhf.gov.uk